My Client2
Frames
- Frame height generally 2440 – refer plans
- All step out walls to have bulkheads i.e. not raked or supported on overhangs (L.Skinner 26.11.10)
- Frames 90mm @ 600 cts only
- Check beam locations due to slight variations in models if using an existing job
- CSD’s = 2 x width + 60mm + pack stud in a 90mm frame 2160 H/H (C.Tadman)
- Generally N2 wind loads if not noted on purchase order check with Mark Butler
- Redcliffe model raised roof detail – Click here
- Internal door head height 2100 including wet areas!
- 35mm internal door jambs located 35mm off junctions (07.08.09)
- External entry / L’dry / L’dry combo door head height 2120.
- External entry doors with side lights to be 1320 or 1230 stud opening width. Check plans and ensure to scale. If unsure increase width & provide pack studs.
- ASD’s as per manufacturers stud openings sizes.
- Brace outside wet areas
Windows
- Check on purchase order. Any discrepancies notify Mark Butler
- Every job should have a window schedule
- Where Southern Star windows are used provide 60mm to height and width on manufacturers sizes (L.Skinner 13/08/15)
- For A & L windows 22.5 degree roof pitch and tiled roof the head height is 2190mm
- Head height for 2740 high frames is 2175mm unless shown or noted otherwise.
- Window head height for jobs with northlight trusses (Kakadu Model) and 10-15 degree roof pitch with infill over windows is 2125mm unless shown or noted otherwise
- Windows at drop-off unless shown otherwise
- Work to brickwork
- Notes
- Shower Niche where indicated 400mm H x 400mm W with 1200mm sill. (M.Butler 23/07/21)
- Not provided, no blocking etc at this stage
Trusses
- 90mm top and bottom chords
- 10mm Plasterboard direct (G.Westbrook19.05.06)
- Generally N2 wind loads if not noted check with Mark Butler
- Redcliffe model raised roof detail – Click here
- All step out walls to have bulkheads i.e. not raked or supported on overhangs (L.Skinner 26.11.10)
- Supply 90×35 MGP10 30/5.4 for bushfire attack 29+ when required. Do Not Cut Back Overhangs. (Ross M 26.02.15)
- Metal fascia unless shown otherwise
- Allow for A/C units in every job (25/08/21)
- Allow for additional ceiling trimmers for change of direction
- Supply Simpson Truss screws and Pryda wall screws in lieu of the existing triple grips and internal wall brackets
Final Check
- Design single & double garage door beams for single dwellings.
- HWD temporary props 100×75 (L.Skinner 22/03/2019)
- 70×20 sill supports
- Allow for additional ceiling trimmers for change of direction
- Supply 90×35 MGP10 30/5.4 for bushfire attack 29+ when required. Do Not Cut Back Overhangs. (Ross M 26.02.15)
- Generally Tillings SJ300 @ 450 cts check plans
- 19mm Yellow tongue flooring (M.Butler 12/02/19)
- Possible request to quote posi joists
- No wet area set downs on two storey jobs (M.Butler 12/02/19)
- Supply 19mm Scyon for wet areas on two storey jobs (M.Butler 12/02/19)
Pricing
- Every job is quoted individually
Quotes & Customer Service
- No soffit linings or A/C sheeting
- No Pergola Material
- No Steel beams unless required in floor system – make a note in the quote
- All else in line with specifications
Leave a Reply